01
Initial Situation
A customer from the aviation industry had been operating SAP BW 7.5 on HANA for over 8 years with approximately 5 TB of data volume and more than 1,200 active objects (InfoProviders, DTPs, process chains). The objective was to migrate to SAP BW/4HANA to improve performance, simplify data models, and ensure long-term maintainability.
02
Project Objectives
- Upgrade to SAP BW/4HANA 2023 release
- Reduction of loading times by at least 30%
- System cleanup with more than 25% fewer objects through consolidation
- Minimal downtime: in-place migration during ongoing operations
03
Approach and Services
- Execution of in-place conversion using SAP conversion tools
- Migration and adaptation of 1,050 objects (InfoCubes, DSOs, ADSOs)
- Conversion of 18 process chains to BW/4HANA-compatible variants
- Implementation of 15 new CDS views for real-time reporting
04
System Optimization
- Archiving of 1.2 TB of historical data (older than 10 years)
- Consolidation of 120 redundant data flows into 80 optimized flows
- Knowledge Transfer and Project Management
- 5 workshops with 30 key users, documentation, and handover of a migration runbook
- Project duration: 14 weeks, go-live over a weekend without unplanned downtime
- Zero data loss confirmed through post-migration checks
05
Results and Added Value
- 37% reduction in loading times in key process chains
- Simplified model landscape with 28% fewer objects
- Business continuity: migration during ongoing operations without impacting reporting processes
- Future-proof platform for predictive analytics and SAP Datasphere integration